Road Closures

◄ Back
March 31, 2017 11:55 AM

202 Lane Closures Scheduled

Right lane closures are scheduled next week on U.S. 202 in East Whiteland and West Whiteland townships, Chester County, for drainage and shoulder reconstruction related to the rehabilitation of two U.S. 202 bridges over Amtrak rail lines, the Pennsylvania Department of Transportation (PennDOT) announced today.

The work schedule is:
Monday, March 20 through Thursday, March 23, from 9:00 AM to 3:00 PM, the right lane is scheduled to close on northbound and southbound U.S. 202 between the U.S. 30 and Boot Road interchanges;
Thursday, March 23, and Sunday, March 26, from 8:00 PM to 5:00 AM, the right lane is scheduled to close on northbound and southbound U.S. 202 between the U.S. 30 and Boot Road interchanges; and
Friday, March 24, and Saturday, March 25, from 8:00 PM to 10:00 AM, the right lane is scheduled to close on northbound and southbound U.S. 202 between the U.S. 30 and Boot Road interchanges.
• Sunday, March 26, through Thursday, March 30, from 8:00 PM to 5:00 AM, lane closures are scheduled on northbound and southbound U.S. 202 between the U.S. 30 and Boot Road interchanges; and
• Friday, March 31, and Saturday, April 1, from 8:00 PM to 10:00 AM, lane closures are scheduled on northbound and southbound U.S. 202 between the U.S. 30 and Boot Road interchanges.
Thursday, April 6, from 8:00 PM to 5:00 AM, lane closures are scheduled on northbound U.S. 202 between the Boot Road and U.S. 30 interchanges;
Friday, April 7, and Saturday, April 8, from 8:00 PM to 10:00 AM, lane closures are scheduled on northbound and southbound U.S. 202 between the U.S. 30 and Boot Road interchanges; and
Sunday, April 9, from 8:00 PM to 5:00 AM, lane closures are scheduled on southbound U.S. 202 between the U.S. 30 and Boot Road interchanges.

Motorists are advised to allow extra time when traveling through the construction area because slowdowns may occur. The work schedule is weather dependent.

The work is part of a $26.4 million project to complete the final phase of the U.S. 202 Section 300 improvement project, which includes the rehabilitation of two U.S. 202 bridges over Amtrak rail lines.

Crews will repair the six-span twin structures by upgrading the support piers; replacing the bridge decks and walls; constructing a retaining wall to stabilize the embankment, rehabilitating existing concrete pavement north of the bridges; and installing new Intelligent Transportation System (ITS) equipment.

In order to maintain two lanes of traffic in each direction on U.S. 202 at all times, construction will be completed in five stages to utilize an Express Lane traffic shift. A temporary traffic pattern will be implemented to carry one lane on the bridge under construction and a second lane on the adjacent bridge, where concrete barriers will separate the lane from the two travel lanes heading in the opposite direction.

Preparations will then be made to shift one lane over of northbound traffic to the southbound side of U.S. 202, where concrete barriers will separate if from the two lanes of southbound traffic. The second northbound lane will remain on the northbound bridge behind construction barrier as the opposite side is rehabilitated under Stage 1 of the bridge work. Once half the northbound bridge is reconstructed, the northbound lane will be shifted onto the newly reconstructed half, and the opposite side of the bridge will be rehabilitated under Stage 2.

When the rehabilitation of the northbound bridge is completed in mid-2018, three lanes of traffic — two northbound lanes and a southbound express lane — will be shifted to the rebuilt northbound bridge. The southbound bridge will then be reconstructed one half-at-a-time under Stages 3-4.

A final construction stage will remove the crossovers and restore the median to complete the project in fall 2019.

In addition to rehabilitating the two U.S. 202 bridges, the improvement project includes restoring U.S. 202 pavement near the U.S. 30 Interchange; rehabilitating the bridge carrying Morstein Road over U.S. 202 in East Goshen Township, Chester County; and installing new highway signs and Dynamic Message System (DMS) structures on U.S. 202 and U.S. 30 in Tredyffrin, East Whiteland and West Whiteland townships, Chester County, and U.S. 202 in Upper Merion Township, Montgomery County.

Facebook Twitter Google Plus Email

Latest Update:

May 18, 2017 9:30 AM

The southbound U.S. 202 exit to the U.S. 30 and Business U.S. 30 Interchange is reduced from two-lanes-to-one for the replacement of deteriorated concrete pavement.

Crews working behind construction barrier are currently removing and replacing the deteriorated concrete from the right lane and shoulder on southbound U.S. 202 from south of the Planebrook Road bridge to the U.S. 30 and Business U.S. 30 Interchange. When completed later this year, traffic will shift to the rebuilt side of the ramp, and concrete replacement will begin on the left lane for much of 2018.

Prior Updates

View All Updates
May 12, 2017 11:21 AM

Due to inclement weather, the Express Lane traffic shift rescheduled for this weekend on U.S. 202 between the U.S. 30 and Boot Road interchanges in East Whiteland and West Whiteland townships, Chester County, has been rescheduled again for the following weekend.

May 4, 2017 10:44 AM

Update to the work schedule:

Due to inclement weather in the forecast, the Express Lane traffic shift originally scheduled for this weekend on U.S. 202 between the U.S. 30 and Boot Road interchanges in East Whiteland and West Whiteland townships, Chester County, has been rescheduled for the following weekend.